Seeing fibre advertised as available in the street does not guarantee that every flat can be connected without common works. The cable route must be followed from the external network to each dwelling.
A building connection has several stages. The operator must reach an entry point and then use or install infrastructure in the common areas before reaching each private unit. A commercial offer sent to one resident does not always describe the condition of that internal route. Before approving work, the co-ownership should therefore obtain a technical survey and compare proposals covering the same scope.
Does the fibre actually reach the flats?
The fixed-network coverage map of the Luxembourg Institute of Regulation (ILR) indicates network availability at an address, but it does not describe the whole internal infrastructure of a building. Between the street and a flat lie the entry point, a possible technical room, vertical ducts and the route across each floor. An obstruction at any of these locations may require common work.
The survey should locate the existing entry, inspect the ducts and identify routes crossing walls, landings or private rooms. It should also state whether an older installation can be reused. Without this survey, two quotations presented as comparable may in fact cover different work.
What information should be requested from the operator or installer?
The proposal should show the route, the equipment to be installed and the locations of any drilling or surface trunking. It must distinguish collective equipment remaining in the common areas from the final connection ordered individually by an occupant. Ask who will restore walls and who will maintain the installation. Another operator’s access to the infrastructure is not, however, a question to put to the installer: it is a right that the law regulates (see below).
Capacity is not only about the present number of dwellings. A properly sized route avoids further building work when another flat requests connection later. In a protected or recently refurbished building, the appearance of landings and façades must be addressed in the project, not after installation.
What should the co-ownership decision contain?
A useful decision says more than “install fibre”. It identifies the accepted plan or quotation, the cost borne collectively, any work charged to each applicant and the person authorised to supervise the project. It also gives the syndic a mandate to conclude the agreement with the operator and the contract with the installer, and to have them settle access to common rooms, working hours, reinstatement and the coverage of any damage. Luxembourg law does not prescribe a model agreement; in the case of an operator’s access request, the agreed terms must be fair and non-discriminatory.
The deployment of high-speed networks and suitable in-building cabling are governed by the Law of 22 March 2017 on measures to reduce the cost of deploying high-speed electronic communications networks and amending the Law of 16 May 1975 on the status of co-ownership of built property (Mémorial A No 356 of 4 April 2017), the technical characteristics of the cabling being set by the Grand-Ducal Regulation of 17 August 2018 (Mémorial A No 1153 of 19 December 2018).
Works to install in-building high-speed network infrastructure in the common parts escape the double majority of Article 17, that is, a majority of the members of the co-owners’ association representing at least three quarters of the voting rights: Article 17, point c), of the Law of 16 May 1975, as replaced by the Law of 30 June 2022 (Mémorial A No 347 of 11 July 2022), expressly excludes them, and they do not appear in Article 16. The decision therefore falls under the Article 15 majority, that is, the majority of the votes of the co-owners present or represented by a duly authorised proxy, all co-owners having been duly convened. The exclusion covers only in-building high-speed network infrastructure, between the network termination point and the first socket (Law of 22 March 2017, Article 2, point 9): cabling beyond the first socket, or works altering the external appearance of the building, fall under a different characterisation, which should be checked before the convening notice is sent.
An operator’s access request, by contrast, is not put to a vote. The syndic who receives it has to answer it: the holder of the right to use the access point and the in-building physical infrastructure is required to grant reasonable access requests, on fair and non-discriminatory terms, and, failing an agreement within two months of the formal request, either party may refer the matter to the ILR, which settles it by a binding decision (Law of 22 March 2017, Articles 9 and 10).
A route passing through a private part requires the agreement of the co-owner concerned: the meeting cannot impose on that co-owner a change to the way their private parts may be enjoyed (Article 18 of the Law of 16 May 1975), and Article 28, as amended by the Law of 22 April 1985, which prohibits any obstruction of works, even inside private parts, covers only works decided under point d) of Article 16 and Article 26.
What should be checked before accepting the work?
Before ducts are closed, retain a route plan and photographs. Check that fire barriers have been properly reinstated, cables are secured and identified without obstructing other services, and common areas have been restored. The file handed to the co-ownership should list the installed equipment, its location, the contractor’s details and the process for connecting another dwelling.
Where possible, test at least one complete route. Acceptance is not merely confirmation that a box is present; it confirms that the common infrastructure can provide the intended connection. This record will prevent the next occupant from having to repeat the whole investigation.